The level of project risk is influenced by:


A、managementcooperation,projectsize,andprojectcosts.
B、projectstructure,leveloftechnicalexpertiseoftheprojectteam,andprojectsize.
C、projecttimeline,projectsize,andend-usercooperation.
D、projectcosts,leveloftechnicalexpertiseoftheprojectteam,andmanagementcooperation.

发布时间:2025-10-27 17:53:52
推荐参考答案 ( 由 题搜搜 官方老师解答 )
答案:B